C
Chris
In Microsoft Project 2007 you have a view called Resource Usage. This view
allows you to load specific days with specific amounts of time to each task.
Is there a way to load your task in such a way in PWA? Or am I missing
something?
Here's an example:
You have a designer who has been assigned a drawing to complete. He needs
to be able to (in PWA) set a simple start-finish date, let's say
1/1/08-2/1/08. Set amount of hours it should take him to complete the task
(not related to start finish) let's say 20hrs. Then load those estimated
hours to specific dates at will. Like 5hrs on the 2nd, 10hrs on the 15th and
the last 8hrs on the 31st. All this in PWA, rather than opening up an entire
schedule in Project to load those hours.
Make sense? Is this a timesheet function?
As always, I appreciate all the help this forum provides.
allows you to load specific days with specific amounts of time to each task.
Is there a way to load your task in such a way in PWA? Or am I missing
something?
Here's an example:
You have a designer who has been assigned a drawing to complete. He needs
to be able to (in PWA) set a simple start-finish date, let's say
1/1/08-2/1/08. Set amount of hours it should take him to complete the task
(not related to start finish) let's say 20hrs. Then load those estimated
hours to specific dates at will. Like 5hrs on the 2nd, 10hrs on the 15th and
the last 8hrs on the 31st. All this in PWA, rather than opening up an entire
schedule in Project to load those hours.
Make sense? Is this a timesheet function?
As always, I appreciate all the help this forum provides.