S
Sekhar
Hi,
I have the following doubts regarding the above Subject.
1.I was trying to do resource loading for about 200 activties under the same Summary bar and with same units for all .But when i select all the activities and key in resource name and the units , its calculating the wrong hours and also the durations get changed.
2.If i have multiple resources for the activities , how can import an excel spread sheet with all the values.
3.The Work hrs does not change after the changing the units..
for ex
ipe fitter - 4.00 units - 4 days - 7.5 hrs -120 hrs
when i change the units the hrs does'nt change from 120 hrs...
Please advise
Thanks in advance
I have the following doubts regarding the above Subject.
1.I was trying to do resource loading for about 200 activties under the same Summary bar and with same units for all .But when i select all the activities and key in resource name and the units , its calculating the wrong hours and also the durations get changed.
2.If i have multiple resources for the activities , how can import an excel spread sheet with all the values.
3.The Work hrs does not change after the changing the units..
for ex
when i change the units the hrs does'nt change from 120 hrs...
Please advise
Thanks in advance