B
Bruce
We are using Project Server 2003, and our organization is divided into
4 major groups with about 5 PMs in each group. These PMs average
about 5 project each, thus more or less 100 active projects the
projects are small and not complex.
My management would like us to begin actively using resource
management features. And the 4 major group managers want to roll up
the individual projects into master project and do resource management
from the masters.
The resource management they are looking for, here, means adjust
assignments so as to balance the work load. These managers could use
PWA / Portfolio Analyzer to help but they want to be resource managers
for the PMs.
Now I'm not the best when it coming to MS Project Server, but is that
master project thing even possible? is there a better way of doing
this?
Thanks
Bruce
4 major groups with about 5 PMs in each group. These PMs average
about 5 project each, thus more or less 100 active projects the
projects are small and not complex.
My management would like us to begin actively using resource
management features. And the 4 major group managers want to roll up
the individual projects into master project and do resource management
from the masters.
The resource management they are looking for, here, means adjust
assignments so as to balance the work load. These managers could use
PWA / Portfolio Analyzer to help but they want to be resource managers
for the PMs.
Now I'm not the best when it coming to MS Project Server, but is that
master project thing even possible? is there a better way of doing
this?
Thanks
Bruce