I am putting together a plan to implement the EPM solution and need to know
if it is possible for the Resource Managers to assign new tasks from the
Project Web Access. And for a team of about 15 people, is it necessary to
have more than 1 Microsoft Project Professional 2003 in order to organize all
the people in our department. I was under the impression that it can be
done, but I am also under the impression that it can spell disaster. Only
one person is allowed to see expenses, and this can be a security issue if
more than one person sees costs in our department. I know you can set
permissions with Project Web Access, but how should we do this? 1 or more
than 1 Microsoft Project Professional 2003? Thanks!
Brett
if it is possible for the Resource Managers to assign new tasks from the
Project Web Access. And for a team of about 15 people, is it necessary to
have more than 1 Microsoft Project Professional 2003 in order to organize all
the people in our department. I was under the impression that it can be
done, but I am also under the impression that it can spell disaster. Only
one person is allowed to see expenses, and this can be a security issue if
more than one person sees costs in our department. I know you can set
permissions with Project Web Access, but how should we do this? 1 or more
than 1 Microsoft Project Professional 2003? Thanks!