Resource Manager to see Resource Tasks

C

Clark

Hello everyone;

I need to be able to set up the Resource Managers to see their resources
tasks. I have setup the Resource Manager to see Resource Assignments, but
this gives them all resources not just the ones that they manage.

Since Project sets up resources as users on the server I need to be able to
combine these all together. Server will not let me merge resource id's with
user Id's.

If I can get the Manager to see the tasks then they can enter the relevnt
information in the timecard for their resources, and also only see their
resources information, rather then company wide.

If anyone can help me I would appreciate it, I am having a tough time with
this.

Jason
 
R

Rod Gill

Have you set up the RBS field? I think this is what defines who works for
who?

In Project Professional, logged into Project Server with an Admin account
open the Enterprise Global and define the resource/management hierarchy in
Resource.OutlineCode30.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
C

Clark

Rod, That sounds like it would work. The only question is how would I can
setup web access so that the Managers see there resource tasks with this.

I can create the hierarchy, but I am not sure how to get web access to use
it right.

Jason
 