Hi all,
When I connect two tasks from different projects, and both tasks have
resources assigned to them, the task that is shown in the project it is
linked to (the one in gray) doesn't show the resource assigned to it. Does
anyone know why this happens? should project act this way?
Thanks
Daniel
When I connect two tasks from different projects, and both tasks have
resources assigned to them, the task that is shown in the project it is
linked to (the one in gray) doesn't show the resource assigned to it. Does
anyone know why this happens? should project act this way?