In a previous post "Resource Names Changing Best Practice" i was given the
below instructions but have a followon question...quotes are what i was
given...rest is my questions.
"In the build team menu (ctrl+T) choose in the left panel (Enterprise
New Question...
We have followed these instructions, and at first glance, it worked fine
....HOWEVER, when I open either of my plans now , I get the message that I
have inactive resources with remaining work.
If this is just a box I click on when opening these plans, so be it! I’m
totally fine with that. If it is something that is going to cause further
problems, please let me know if there’s something else I should do.
Please advise. Thanks
In a previous post "Resource Names Changing Best Practice" i was given the
below instructions but have a followon question...quotes are what i was
given...rest is my questions.
"In the build team menu (ctrl+T) choose in the left panel (Enterprise
resource) the name of the resource that will do the work and in the right
panel (Project Team resource) the name of the resource leaving and select
replace.
New resource will be allocated instead of the previous one on all the task
of the project (even those completed)."
New Question...
We have followed these instructions, and at first glance, it worked fine
....HOWEVER, when I open either of my plans now , I get the message that I
have inactive resources with remaining work.
If this is just a box I click on when opening these plans, so be it! I’m
totally fine with that. If it is something that is going to cause further
problems, please let me know if there’s something else I should do.
Please advise. Thanks