J
Jeff L
I have a task defined as fixed units and start as soon as
possible. I assign 2 resources, each at 100% for a
duration of 2 days. Each resource is assigned 16 hours
work.
I then change the units for either the 1st or 2nd resource
to 50%, leaving the other unchanged. Then I change the
duration from 2 days to 6 days. The resource that I
changed the units to 50% is scheduled out for the entire 6
day duration at the appropriate 50%, but the resource
whose units were not changed (still at 100%) does not get
scheduled beyond the original 2 days. If I extend the
duration to 20 days, the 50% resource gets scheduled out
but the other resource still remains at 2 days.
If I don't change the units on either (leave them both at
100%) and change the duration, they both have their
schedules adjusted out correctly.
If I delete the resource that was left unchanged (100%),
then re-add them, they get setup with the correct number
of hours for the duration (6 days, 48 hours).
What is happening? What do I need to do to correct this?
--Jeff
possible. I assign 2 resources, each at 100% for a
duration of 2 days. Each resource is assigned 16 hours
work.
I then change the units for either the 1st or 2nd resource
to 50%, leaving the other unchanged. Then I change the
duration from 2 days to 6 days. The resource that I
changed the units to 50% is scheduled out for the entire 6
day duration at the appropriate 50%, but the resource
whose units were not changed (still at 100%) does not get
scheduled beyond the original 2 days. If I extend the
duration to 20 days, the 50% resource gets scheduled out
but the other resource still remains at 2 days.
If I don't change the units on either (leave them both at
100%) and change the duration, they both have their
schedules adjusted out correctly.
If I delete the resource that was left unchanged (100%),
then re-add them, they get setup with the correct number
of hours for the duration (6 days, 48 hours).
What is happening? What do I need to do to correct this?
--Jeff