As there must be a setting to allow this somewhere but I am missing
this
knowledge, I am scratching my head.
Bawbee
:
Hello Bawbee,
I'm glad you found a method to solve your problem although it still
doesn't make a great deal of sense to me. My understanding was you
had changed a resource's calendar to allow 12 hour work days.
Did you have the resource assigned at 100% to the task? Are the
tasks
of short duration - 1 day or less? If the task's duration is one
day
and you assign a resource to the task -- even though the resource
calendar *allows* 12 hours per day you will only see 8 hours of
work
assuming setting for hours per day is equal to 8.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
Julie,
I did manage to work-around this by manually entering the
requirements in
the Resource Usage view. The thing is, 'most' of the usage fields
were
already set to 12. (?)
Bawbee
:
Hi Julie,
In Task Usage View it shows 8 hours per day.
I did as you suggested with the task calendar (I had it set to
the
same as
the resource) and set it to 'None'. This made no difference, the
Task Usage
still shows 8 hours per day.
Bawbee
:
Hello Bawbee,
If you look at the Task Usage view, do you see 8 hours or 12
hours of
work? You haven't assigned a task calendar to the task have
you?
Double click on the task to view the task information dialog
box,
click the advanced tab. Under Calendars ensure it is set to
"none".
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
I have created 2 resources for 12 hours per day working but
they
only
show 8
hours for costs. The resources have been assigned a calendar
with a
work-time
of 0800-2000 and 7 days per week. The relevant tasks have
also
been
assigned
the same calendar. How can/do I show these resources working
12
hours per day?
Any assistance appreciated.