How can I change the units of the summary rows in the usage views?

The assignment rows are in days and the summary is in hours.

Please note that when the same plan is opened in different machine by
different user the summary units similar to the units in the tasks rows.

Ein
 
G

Gérard Ducouret

Hello Ein,
Are you speaking about the Duration field ?

Try : Tools / Options / Schedule / Duration is entered in... Days

Hope this helps,

Gérard Ducouret
 
E

ein

Hi,
I'm talking about the work field, I'v already tried your suggestion, it
didn't work. The problem is the differance between the summary work units
(hrs) and the work
units displayed at the task level.
Ein
 
G

Gérard Ducouret

Hi,
I tried on both 2002 and 2003 versions : it works fine for me on the Work
field too. All the work values are using the same unit (hr or day) I choose
in Tools / Options / Schedule.

Gérard Ducouret
 