K
Kevin M
Greetings,
I'm flying solo now on a Project 2003 EPMS a consultant helped out with on a
lot of the initial configuration as I was training up, and am noticing that
some outline codes contain only 1st-level items in the lookup table.
Since Project-level custom fields are also available in Portfolio Analyzer
(the main place we'll be using the coding for analysis) I was wondering why
it might be better to use an outline code to define, say, a resource's cost
center when I could assign a Resource Enterprise Number to contain the same
data and use the same values in the lookup table for the Number value list.
Other than saving me the effort, is there any reason to use outline coding
rather than project and resource level value lists when all items in the
lookup table are 1st-level?
Thanks,
Kevin
I'm flying solo now on a Project 2003 EPMS a consultant helped out with on a
lot of the initial configuration as I was training up, and am noticing that
some outline codes contain only 1st-level items in the lookup table.
Since Project-level custom fields are also available in Portfolio Analyzer
(the main place we'll be using the coding for analysis) I was wondering why
it might be better to use an outline code to define, say, a resource's cost
center when I could assign a Resource Enterprise Number to contain the same
data and use the same values in the lookup table for the Number value list.
Other than saving me the effort, is there any reason to use outline coding
rather than project and resource level value lists when all items in the
lookup table are 1st-level?
Thanks,
Kevin