C
Caren
I was wondering if anyone could help me with my overallocated
resources. I am trying to use a resource pool and link several
projects to it. As it stands, I have dedicated one resource 100% to
three different projects, and I am finding that my resource is
overallocated when his total work time is less than one day per any
given day. In other words, the resource pool is telling me that he is
overallocated when his total work for the day is only 0.8day. I have
checked the resource schedule (a standard 8hr work day, no holidays,
etc.), so I don't think it has to do with that (although I could be
wrong). I have also tried dedicating the single resource 33% to each
project, just to see what the resource summary does. This didn't work
either.
Basically I am just trying to use a resource pool file as a summary
for all of the projects that my resources are working on, that way I
can really tell when a resource has been overallocated or if
additional resources are needed at different phases of the various
projects. If anyone can shed some light on the subject that would be
great! I am also open to any suggestions for alternate methods.
Thanks!
~Caren
resources. I am trying to use a resource pool and link several
projects to it. As it stands, I have dedicated one resource 100% to
three different projects, and I am finding that my resource is
overallocated when his total work time is less than one day per any
given day. In other words, the resource pool is telling me that he is
overallocated when his total work for the day is only 0.8day. I have
checked the resource schedule (a standard 8hr work day, no holidays,
etc.), so I don't think it has to do with that (although I could be
wrong). I have also tried dedicating the single resource 33% to each
project, just to see what the resource summary does. This didn't work
either.
Basically I am just trying to use a resource pool file as a summary
for all of the projects that my resources are working on, that way I
can really tell when a resource has been overallocated or if
additional resources are needed at different phases of the various
projects. If anyone can shed some light on the subject that would be
great! I am also open to any suggestions for alternate methods.
Thanks!
~Caren