K
Kristen
Why does project sometime flag a resource as overallocated when they are not?
For example, sometime when I look at my resource usage view to see if there
are overallocations a resource is highlighted in red so i look to that
particular day and it only shows the resource working 6 hrs (should be a 9
hour day) and it is in red and no matter what I do it won't show that they
are not overallocated.
For example, sometime when I look at my resource usage view to see if there
are overallocations a resource is highlighted in red so i look to that
particular day and it only shows the resource working 6 hrs (should be a 9
hour day) and it is in red and no matter what I do it won't show that they
are not overallocated.