M
Matt
I am trying to understand why and how the resource percentage changes..I put
a task for fix duration effort driven with a start date of 6/14 and date of
6/27. we are using our calendar (omits weekends) and I have scheduled this
task for 10 day duration with a dead line on 6/27 and a start no earlier then
6/14 date. I schedule the resource for 50% of his time ..total task should
be 40 hrs which equates to 4 hrs a day for 10 days. I also have effort
driven checked and estimated time unchecked. I added time for the task as
follows : 6/14 - 10 hrs, 6/15 - 10 hrs - 6/18 - 10 hrs, 6/19 - 5 hrs and 6/20
- 3 hrs which is a total of 38 hrs applied to a 40 hr task. When I do the
update from PWA it changes the reource percentage to 125 % and changes the
hrs from 4 hrs per day to .4 for the remaing 5 workdays. which ends on 6/27.
I would have thought that the resource percentage would have decreased since
the hrs ar less then the original hrs assigned..can you please provide some
guidence as to why this happens...I appreciate your help...thanks
a task for fix duration effort driven with a start date of 6/14 and date of
6/27. we are using our calendar (omits weekends) and I have scheduled this
task for 10 day duration with a dead line on 6/27 and a start no earlier then
6/14 date. I schedule the resource for 50% of his time ..total task should
be 40 hrs which equates to 4 hrs a day for 10 days. I also have effort
driven checked and estimated time unchecked. I added time for the task as
follows : 6/14 - 10 hrs, 6/15 - 10 hrs - 6/18 - 10 hrs, 6/19 - 5 hrs and 6/20
- 3 hrs which is a total of 38 hrs applied to a 40 hr task. When I do the
update from PWA it changes the reource percentage to 125 % and changes the
hrs from 4 hrs per day to .4 for the remaing 5 workdays. which ends on 6/27.
I would have thought that the resource percentage would have decreased since
the hrs ar less then the original hrs assigned..can you please provide some
guidence as to why this happens...I appreciate your help...thanks