P
Pete Nathan, PMP
Does anyone know of a way to set up a combo of permissions for groups and
categories so that PMs using Project Pro 2003 can build a team from the
Project Server 2003 enterprise resource pool without having the rate columns
available for the PMs to see? This appears to be an issue in how Project Pro
2003 (as a client) handles security from Project Server.
The goal is to allow a PM using Project Pro to:
1. load resources from the enterprise resource pool,
2. deny the PM the ability to see hourly rates for the resource (Resource
Sheet view & Resource info dialog box),
3. permit the calc of summary cost data and EVM for reporting.
In Project Pro 2003, I can hide the Std. Rate and Ovt. Rate columns on the
resource sheet view in the global enterprise template. However, if a PM just
clicks on a resource name, he’ll bring up the enterprise Resource Information
dialog box and have access to rates. Or, if he right mouse clicks, he can
insert the Std. Rate column back into the view. Is there such a security
lockout option available in the Enterprise Global template at the column or
table level? Would deleting the Resource Cost Table in Organizer and in the
Enterprise Global template be an acceptable work around? Do I have to alter
the Global.mpt on each PM’s Project Pro? Do I have to do something like
setting SQL Server column level permissions in MSP_WEB_RESOURCES to deny PMs
from viewing the Standard Rate column?
The two other work around that I’ve tried that are acceptable is to make the
Std Cost column either $1 and use this as an additional hour field, or to
establish an organizational-wide standard rate that is a ballpark rate.
Using this approach, we’d get the EVM and cost trends, but not actuals. In
either case using this scenario, we’d have to give the actual hours (burn
rate) to a financial analyst to determine actual project costs for reporting
to execs.
Thanks in advance,
Pete Nathan, PMP
Author, PMP Certification For Dummies
categories so that PMs using Project Pro 2003 can build a team from the
Project Server 2003 enterprise resource pool without having the rate columns
available for the PMs to see? This appears to be an issue in how Project Pro
2003 (as a client) handles security from Project Server.
The goal is to allow a PM using Project Pro to:
1. load resources from the enterprise resource pool,
2. deny the PM the ability to see hourly rates for the resource (Resource
Sheet view & Resource info dialog box),
3. permit the calc of summary cost data and EVM for reporting.
In Project Pro 2003, I can hide the Std. Rate and Ovt. Rate columns on the
resource sheet view in the global enterprise template. However, if a PM just
clicks on a resource name, he’ll bring up the enterprise Resource Information
dialog box and have access to rates. Or, if he right mouse clicks, he can
insert the Std. Rate column back into the view. Is there such a security
lockout option available in the Enterprise Global template at the column or
table level? Would deleting the Resource Cost Table in Organizer and in the
Enterprise Global template be an acceptable work around? Do I have to alter
the Global.mpt on each PM’s Project Pro? Do I have to do something like
setting SQL Server column level permissions in MSP_WEB_RESOURCES to deny PMs
from viewing the Standard Rate column?
The two other work around that I’ve tried that are acceptable is to make the
Std Cost column either $1 and use this as an additional hour field, or to
establish an organizational-wide standard rate that is a ballpark rate.
Using this approach, we’d get the EVM and cost trends, but not actuals. In
either case using this scenario, we’d have to give the actual hours (burn
rate) to a financial analyst to determine actual project costs for reporting
to execs.
Thanks in advance,
Pete Nathan, PMP
Author, PMP Certification For Dummies