Resource placeholders

D

Dan

I am working with MS Project 2003. I am developing a template for my
organization which will utilize a resource pool. I would like to set up the
template with predefined "Roles" and effort for each task. Is there a way to
define a "Role" so that when the resources are defined for the project a
resource can be filled in for the Role? I am looking for a more elegant
solution than adding dummy resources. I would like to maintain the role that
the resource is playing on the project.
 
R

Rod Gill

Dummy resources are your only option I'm afraid, even with Project Server.

Make sure you don't link templates to resource pools as that's a sure fired
way to corrupt resource workloads and create file corruptions by messing
with links when the template is saved with a new name.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 