Resource Plan and Leveling

G

graffer54

In our project, resource plans have been created for some of the resources.
The plan was then leveled manually for these resources. After leveling, does
Project still adjust dates based on the resource plan? For example, we moved
out Task A which moved out the dates for Task B, even though there was slack
available. Any suggestions?
 
J

Jan De Messemaeker

Hi,

There must be a reason (resource availability or links) but I'm not
clairvoyant so I can't guess.
If you want me to have a look you can send the file to
jandemesATprom-ade.be
I'll have a look

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
G

graffer54

I am unable to send the plan. Does anyone have any other
suggestions/ideas/comments?
 
D

Dave

graffer54 said:
In our project, resource plans have been created for some of the resources.
The plan was then leveled manually for these resources. After leveling, does
Project still adjust dates based on the resource plan? For example, we moved
out Task A which moved out the dates for Task B, even though there was slack
available. Any suggestions?

Are you sure you are looking at all the tasks? Maybe there is a filter
applied.

Could one of the tasks be a hammock task?
 
G

graffer54

I discovered that when a task is moved, Project will decrease slack but not
leveling delay. All I have to do is keep an eye on leveling delay and
decrease it where possible to maintain my original dates.
 