M
Marlene52
Does anyone know how a resources calculation is done via the Resource Plan?
If I mark a resource 50% for the month and that month has 176 hours, I would
expect to see 88 hours, instead I see something like 134 hours.
anyone have any suggestions??
Thanks and we are on MSP 2007 and have everything but the April CU installed
Marlene
If I mark a resource 50% for the month and that month has 176 hours, I would
expect to see 88 hours, instead I see something like 134 hours.
anyone have any suggestions??
Thanks and we are on MSP 2007 and have everything but the April CU installed
Marlene