Resource Plan calculations

M

Marlene52

I am getting a strange number when I am trying to use a Resource Plan on a
current project. The capacity for a month on a particular resource is 144
and the Resource Plan that is associated with the project shows that resource
at 50%, I assumed I would get 72 hours and instead I am getting 196????
Any help or suggestions would be helpful.
One more thing to note
the project was already started with resource assignments, however in the
particular month I am looking at, there is no project assignment for this
person. the resource plan was added after the plan was already up and
running and accepting updates.
Thanks,
Marlene
 