I am getting a strange number when I am trying to use a Resource Plan on a
current project. The capacity for a month on a particular resource is 144
and the Resource Plan that is associated with the project shows that resource
at 50%, I assumed I would get 72 hours and instead I am getting 196????
Any help or suggestions would be helpful.
One more thing to note
the project was already started with resource assignments, however in the
particular month I am looking at, there is no project assignment for this
person. the resource plan was added after the plan was already up and
running and accepting updates.
Thanks,
Marlene
current project. The capacity for a month on a particular resource is 144
and the Resource Plan that is associated with the project shows that resource
at 50%, I assumed I would get 72 hours and instead I am getting 196????
Any help or suggestions would be helpful.
One more thing to note
the project was already started with resource assignments, however in the
particular month I am looking at, there is no project assignment for this
person. the resource plan was added after the plan was already up and
running and accepting updates.
Thanks,
Marlene