Resource plan gone and disabled after administrative restore

R

Rickard

Using Project Server 2007 + SP2 + April 2009 CU

After successfully restoring an Activity Plan using Server Settings ->
Administrative Restore we've noticed that the resource plan for the Activity
Plan is gone. Fair enough, maybe resource plans are not included in an
administrative backup. BUT the besides that, the Build Team button in the
resource plan view is "greyed out" and if I choose Calculate Resource
Utilization From -> Resource Plan I get the error message "Selected item does
not exist". Is this a bug and is there a fix for it? How can we create a new
resource plan for the Activity Plan? I've recreated this scenario in our test
environment as well with the same result. I don't think this has anything to
do with permissions because I perform this operation as an administrator.

Please help!!
 