Resource plan - kow it communicate with Database

R

Rafal_Paczynski

Hello,

I have error message when works with Resource Plan. It happens for one user
only.That user is called Henrik, each time when we are trying to save
Resource Plan after adding Henrik to the resource plan (we tried in many
different resource plans each time is that some) we can see GENERAL ERROR. I
was checking in databases and I can find resource plan under Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I can see
other resources assigned to that resource plan (and that is perfect). In this
table I can't see henrik account assigned to the resource plan howether under
PWA web page I can see his account. Could you plase explain to me if is any
temporary database where that account is so I can see it under PWA before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have that problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE, Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean asyncCall)
at System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative updates.

Thank you in advance
Michal
 
R

Rafal_Paczynski

Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a project
plan. He is reporting his time on PWA everyday. Is no problem with reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan. Each time we
assign press Save or Save and Publish we have error General error: Work value
used is invalid. (Use this error information along with other errors to find
out the cause of the problem.)

I was also informed that that some problem is now for one more resource.

BR
Rafal



Gary L. Chefetz said:
Are you certain that Henrik is a resource that can be assigned to tasks in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hello,

I have error message when works with Resource Plan. It happens for one
user
only.That user is called Henrik, each time when we are trying to save
Resource Plan after adding Henrik to the resource plan (we tried in many
different resource plans each time is that some) we can see GENERAL ERROR.
I
was checking in databases and I can find resource plan under Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I can see
other resources assigned to that resource plan (and that is perfect). In
this
table I can't see henrik account assigned to the resource plan howether
under
PWA web page I can see his account. Could you plase explain to me if is
any
temporary database where that account is so I can see it under PWA before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE, Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean asyncCall)
at System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative updates.

Thank you in advance
Michal
 
R

Rafal_Paczynski

Hi,

I just discovered something, when in resource Plan Column Interval is set up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


Rafal_Paczynski said:
Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a project
plan. He is reporting his time on PWA everyday. Is no problem with reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan. Each time we
assign press Save or Save and Publish we have error General error: Work value
used is invalid. (Use this error information along with other errors to find
out the cause of the problem.)

I was also informed that that some problem is now for one more resource.

BR
Rafal



Gary L. Chefetz said:
Are you certain that Henrik is a resource that can be assigned to tasks in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hello,

I have error message when works with Resource Plan. It happens for one
user
only.That user is called Henrik, each time when we are trying to save
Resource Plan after adding Henrik to the resource plan (we tried in many
different resource plans each time is that some) we can see GENERAL ERROR.
I
was checking in databases and I can find resource plan under Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I can see
other resources assigned to that resource plan (and that is perfect). In
this
table I can't see henrik account assigned to the resource plan howether
under
PWA web page I can see his account. Could you plase explain to me if is
any
temporary database where that account is so I can see it under PWA before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE, Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean asyncCall)
at System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative updates.

Thank you in advance
Michal
 
G

Gary L. Chefetz

Interesting, what language version are you using? This may be an anomaly in
Project Server or it may be locale specific. Can you share the actual error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi,

I just discovered something, when in resource Plan Column Interval is set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


Rafal_Paczynski said:
Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a
project
plan. He is reporting his time on PWA everyday. Is no problem with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan. Each time
we
assign press Save or Save and Publish we have error General error: Work
value
used is invalid. (Use this error information along with other errors to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more resource.

BR
Rafal



Gary L. Chefetz said:
Are you certain that Henrik is a resource that can be assigned to tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It happens for
one
user
only.That user is called Henrik, each time when we are trying to save
Resource Plan after adding Henrik to the resource plan (we tried in
many
different resource plans each time is that some) we can see GENERAL
ERROR.
I
was checking in databases and I can find resource plan under Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I
can see
other resources assigned to that resource plan (and that is perfect).
In
this
table I can't see henrik account assigned to the resource plan
howether
under
PWA web page I can see his account. Could you plase explain to me if
is
any
temporary database where that account is so I can see it under PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE, Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean
asyncCall)
at System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative
updates.

Thank you in advance
Michal
 
R

Rafal_Paczynski

Hi Gary,

Sory for a late replay. And by the way "Ultimate Learning guide" very good
book :))

Well our settings on
1) Server 2003 SP2:
- English (United States)
location United States
2) Project Server 2007 ( withDec. cumulative update):
- from Project Web Access > Site Settings > Regional Settings English
(United States)


The most strange think is that "General Error" is only on one user per
Resource Plan, and only when period time is month.


Please let me know if you have any idea of that behaviour.

That is the error message:
---------------------
05/29/2009 13:10:34.72 w3wp.exe (0x0890)
0x163C Project Server Project Server - General
0 Medium PWA:http://pwa.../DITRM, SSP:MSPROJECTSSP, User:doamin\username,
PSI: ResourcePlan.QueueUpdateResourcePlan Unset Attributes: PSError:
GeneralWorkInvalid Unset attributes list:
column 351bcb8f-7a5f-47be-91a9-751fc4d26a2a
------


05/29/2009 13:10:34.72 w3wp.exe (0x23EC)
0x1CE8 Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE, Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean asyncCall)
at System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

-----------



Thank you for help :)

Rafal Paczynski


Gary L. Chefetz said:
Interesting, what language version are you using? This may be an anomaly in
Project Server or it may be locale specific. Can you share the actual error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi,

I just discovered something, when in resource Plan Column Interval is set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


Rafal_Paczynski said:
Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a
project
plan. He is reporting his time on PWA everyday. Is no problem with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan. Each time
we
assign press Save or Save and Publish we have error General error: Work
value
used is invalid. (Use this error information along with other errors to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more resource.

BR
Rafal



:

Are you certain that Henrik is a resource that can be assigned to tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It happens for
one
user
only.That user is called Henrik, each time when we are trying to save
Resource Plan after adding Henrik to the resource plan (we tried in
many
different resource plans each time is that some) we can see GENERAL
ERROR.
I
was checking in databases and I can find resource plan under Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I
can see
other resources assigned to that resource plan (and that is perfect).
In
this
table I can't see henrik account assigned to the resource plan
howether
under
PWA web page I can see his account. Could you plase explain to me if
is
any
temporary database where that account is so I can see it under PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE, Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean
asyncCall)
at System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative
updates.

Thank you in advance
Michal
 
R

Rafal_Paczynski

Hi Again,

I forgot to add, that in resource Plan:
Cloumn Interval - Months
Work units - Days (it is also failing with HOURS)

Thanks for help

Rafal Paczynski




Gary L. Chefetz said:
Interesting, what language version are you using? This may be an anomaly in
Project Server or it may be locale specific. Can you share the actual error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi,

I just discovered something, when in resource Plan Column Interval is set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


Rafal_Paczynski said:
Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a
project
plan. He is reporting his time on PWA everyday. Is no problem with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan. Each time
we
assign press Save or Save and Publish we have error General error: Work
value
used is invalid. (Use this error information along with other errors to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more resource.

BR
Rafal



:

Are you certain that Henrik is a resource that can be assigned to tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It happens for
one
user
only.That user is called Henrik, each time when we are trying to save
Resource Plan after adding Henrik to the resource plan (we tried in
many
different resource plans each time is that some) we can see GENERAL
ERROR.
I
was checking in databases and I can find resource plan under Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I
can see
other resources assigned to that resource plan (and that is perfect).
In
this
table I can't see henrik account assigned to the resource plan
howether
under
PWA web page I can see his account. Could you plase explain to me if
is
any
temporary database where that account is so I can see it under PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE, Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean
asyncCall)
at System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative
updates.

Thank you in advance
Michal
 
G

Gary L. Chefetz

Rafal:

Are you planning on installing SP2 anytime soon? If so, I'd be curious
whether that resolves the issue, otherwise I'm leaning toward thinking this
may be the result of corruption in the db. I want to be sure that I
understand that this problem only occurs with two specific resources? If
that's the case, it points more toward those resource records than the
Resource plan functionality.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi Again,

I forgot to add, that in resource Plan:
Cloumn Interval - Months
Work units - Days (it is also failing with HOURS)

Thanks for help

Rafal Paczynski




Gary L. Chefetz said:
Interesting, what language version are you using? This may be an anomaly
in
Project Server or it may be locale specific. Can you share the actual
error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi,

I just discovered something, when in resource Plan Column Interval is
set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


:

Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a
project
plan. He is reporting his time on PWA everyday. Is no problem with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan. Each
time
we
assign press Save or Save and Publish we have error General error:
Work
value
used is invalid. (Use this error information along with other errors
to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more
resource.

BR
Rafal



:

Are you certain that Henrik is a resource that can be assigned to
tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It happens for
one
user
only.That user is called Henrik, each time when we are trying to
save
Resource Plan after adding Henrik to the resource plan (we tried
in
many
different resource plans each time is that some) we can see
GENERAL
ERROR.
I
was checking in databases and I can find resource plan under
Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I
can see
other resources assigned to that resource plan (and that is
perfect).
In
this
table I can't see henrik account assigned to the resource plan
howether
under
PWA web page I can see his account. Could you plase explain to me
if
is
any
temporary database where that account is so I can see it under PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have
that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE,
Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean
asyncCall)
at
System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative
updates.

Thank you in advance
Michal
 
R

Rafal_Paczynski

Hi Gary,

I would like to install SP2 asap. Howether I think it can take a long while
between we will implemend SP2 on prod. servers. That is because we are about
to prepare SP2 for client first. After rolling our SP2 to Project 2007 Pro we
will start installing SP2 on test and prod servers.


Problem situation:
All my colleaques from IT are reporting time (every week/day) on PWA. There
are not problems with reporting time and importing timesheets (except some
small problems sometimes). Whenone of our colleaques is added on Resource
Plans and:
Work Units : days or hours
Column Interval: Months (the most popular and easy for everybody).

We have General Error message as described before.

I think that error is only on specific resource (but this resource has no
problem with reporting time) We checked that account many times - seems to be
configured correctly as all others.

But Resource Plan works when Column Interval is set up for weeks - that is
strange.


Thank you for any help.

BR
Rafal Paczynski



Gary L. Chefetz said:
Rafal:

Are you planning on installing SP2 anytime soon? If so, I'd be curious
whether that resolves the issue, otherwise I'm leaning toward thinking this
may be the result of corruption in the db. I want to be sure that I
understand that this problem only occurs with two specific resources? If
that's the case, it points more toward those resource records than the
Resource plan functionality.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi Again,

I forgot to add, that in resource Plan:
Cloumn Interval - Months
Work units - Days (it is also failing with HOURS)

Thanks for help

Rafal Paczynski




Gary L. Chefetz said:
Interesting, what language version are you using? This may be an anomaly
in
Project Server or it may be locale specific. Can you share the actual
error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Hi,

I just discovered something, when in resource Plan Column Interval is
set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


:

Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a
project
plan. He is reporting his time on PWA everyday. Is no problem with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan. Each
time
we
assign press Save or Save and Publish we have error General error:
Work
value
used is invalid. (Use this error information along with other errors
to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more
resource.

BR
Rafal



:

Are you certain that Henrik is a resource that can be assigned to
tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It happens for
one
user
only.That user is called Henrik, each time when we are trying to
save
Resource Plan after adding Henrik to the resource plan (we tried
in
many
different resource plans each time is that some) we can see
GENERAL
ERROR.
I
was checking in databases and I can find resource plan under
Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this table I
can see
other resources assigned to that resource plan (and that is
perfect).
In
this
table I can't see henrik account assigned to the resource plan
howether
under
PWA web page I can see his account. Could you plase explain to me
if
is
any
temporary database where that account is so I can see it under PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have
that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException: ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE,
Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean
asyncCall)
at
System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December Cumulative
updates.

Thank you in advance
Michal
 
G

Gary L. Chefetz

Rafal:

I can't reproduce this in a test system and I haven't seen anyone report
this before, so I wonder if this isn't a similar situation to your task
problem where there's some corruption causing it. I'll dig around and see if
I can come up with anything.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi Gary,

I would like to install SP2 asap. Howether I think it can take a long
while
between we will implemend SP2 on prod. servers. That is because we are
about
to prepare SP2 for client first. After rolling our SP2 to Project 2007 Pro
we
will start installing SP2 on test and prod servers.


Problem situation:
All my colleaques from IT are reporting time (every week/day) on PWA.
There
are not problems with reporting time and importing timesheets (except some
small problems sometimes). Whenone of our colleaques is added on Resource
Plans and:
Work Units : days or hours
Column Interval: Months (the most popular and easy for everybody).

We have General Error message as described before.

I think that error is only on specific resource (but this resource has no
problem with reporting time) We checked that account many times - seems to
be
configured correctly as all others.

But Resource Plan works when Column Interval is set up for weeks - that is
strange.


Thank you for any help.

BR
Rafal Paczynski



Gary L. Chefetz said:
Rafal:

Are you planning on installing SP2 anytime soon? If so, I'd be curious
whether that resolves the issue, otherwise I'm leaning toward thinking
this
may be the result of corruption in the db. I want to be sure that I
understand that this problem only occurs with two specific resources? If
that's the case, it points more toward those resource records than the
Resource plan functionality.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi Again,

I forgot to add, that in resource Plan:
Cloumn Interval - Months
Work units - Days (it is also failing with HOURS)

Thanks for help

Rafal Paczynski




:

Interesting, what language version are you using? This may be an
anomaly
in
Project Server or it may be locale specific. Can you share the actual
error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Hi,

I just discovered something, when in resource Plan Column Interval
is
set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


:

Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a
project
plan. He is reporting his time on PWA everyday. Is no problem with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan.
Each
time
we
assign press Save or Save and Publish we have error General error:
Work
value
used is invalid. (Use this error information along with other
errors
to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more
resource.

BR
Rafal



:

Are you certain that Henrik is a resource that can be assigned to
tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It happens
for
one
user
only.That user is called Henrik, each time when we are trying
to
save
Resource Plan after adding Henrik to the resource plan (we
tried
in
many
different resource plans each time is that some) we can see
GENERAL
ERROR.
I
was checking in databases and I can find resource plan under
Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this
table I
can see
other resources assigned to that resource plan (and that is
perfect).
In
this
table I can't see henrik account assigned to the resource plan
howether
under
PWA web page I can see his account. Could you plase explain to
me
if
is
any
temporary database where that account is so I can see it under
PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have
that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException:
ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE,
Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean
asyncCall)
at
System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December
Cumulative
updates.

Thank you in advance
Michal
 
R

Rafal_Paczynski

Hi Gary,

Thanks for help.
The most strange think is that I was trying to reporoduce that on test
servers using that some reource which generate problem. And on test I can't
reproduce it. I have that problem only on production. (Our test is copy from
prod)

If you will have anything plase let me know, some of our users are very
annoyed by that problem.

Thank you in advance :)

I created case for Microsoft, they can reproduce that error, but for now do
not know solution.


Gary L. Chefetz said:
Rafal:

I can't reproduce this in a test system and I haven't seen anyone report
this before, so I wonder if this isn't a similar situation to your task
problem where there's some corruption causing it. I'll dig around and see if
I can come up with anything.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi Gary,

I would like to install SP2 asap. Howether I think it can take a long
while
between we will implemend SP2 on prod. servers. That is because we are
about
to prepare SP2 for client first. After rolling our SP2 to Project 2007 Pro
we
will start installing SP2 on test and prod servers.


Problem situation:
All my colleaques from IT are reporting time (every week/day) on PWA.
There
are not problems with reporting time and importing timesheets (except some
small problems sometimes). Whenone of our colleaques is added on Resource
Plans and:
Work Units : days or hours
Column Interval: Months (the most popular and easy for everybody).

We have General Error message as described before.

I think that error is only on specific resource (but this resource has no
problem with reporting time) We checked that account many times - seems to
be
configured correctly as all others.

But Resource Plan works when Column Interval is set up for weeks - that is
strange.


Thank you for any help.

BR
Rafal Paczynski



Gary L. Chefetz said:
Rafal:

Are you planning on installing SP2 anytime soon? If so, I'd be curious
whether that resolves the issue, otherwise I'm leaning toward thinking
this
may be the result of corruption in the db. I want to be sure that I
understand that this problem only occurs with two specific resources? If
that's the case, it points more toward those resource records than the
Resource plan functionality.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Hi Again,

I forgot to add, that in resource Plan:
Cloumn Interval - Months
Work units - Days (it is also failing with HOURS)

Thanks for help

Rafal Paczynski




:

Interesting, what language version are you using? This may be an
anomaly
in
Project Server or it may be locale specific. Can you share the actual
error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Hi,

I just discovered something, when in resource Plan Column Interval
is
set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


:

Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned in a
project
plan. He is reporting his time on PWA everyday. Is no problem with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan.
Each
time
we
assign press Save or Save and Publish we have error General error:
Work
value
used is invalid. (Use this error information along with other
errors
to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more
resource.

BR
Rafal



:

Are you certain that Henrik is a resource that can be assigned to
tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It happens
for
one
user
only.That user is called Henrik, each time when we are trying
to
save
Resource Plan after adding Henrik to the resource plan (we
tried
in
many
different resource plans each time is that some) we can see
GENERAL
ERROR.
I
was checking in databases and I can find resource plan under
Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this
table I
can see
other resources assigned to that resource plan (and that is
perfect).
In
this
table I can't see henrik account assigned to the resource plan
howether
under
PWA web page I can see his account. Could you plase explain to
me
if
is
any
temporary database where that account is so I can see it under
PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not have
that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server - General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException:
ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE,
Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream, Boolean
asyncCall)
at
System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December
Cumulative
updates.

Thank you in advance
Michal
 
G

Gary L. Chefetz

Rafal:

If you've opened a case with MSFT, you'll probably get to the bottom of it,
maybe not as soon as you like, but please post the results back to this
thread so we can all learn from it. Thanks!

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi Gary,

Thanks for help.
The most strange think is that I was trying to reporoduce that on test
servers using that some reource which generate problem. And on test I
can't
reproduce it. I have that problem only on production. (Our test is copy
from
prod)

If you will have anything plase let me know, some of our users are very
annoyed by that problem.

Thank you in advance :)

I created case for Microsoft, they can reproduce that error, but for now
do
not know solution.


Gary L. Chefetz said:
Rafal:

I can't reproduce this in a test system and I haven't seen anyone report
this before, so I wonder if this isn't a similar situation to your task
problem where there's some corruption causing it. I'll dig around and see
if
I can come up with anything.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Rafal_Paczynski said:
Hi Gary,

I would like to install SP2 asap. Howether I think it can take a long
while
between we will implemend SP2 on prod. servers. That is because we are
about
to prepare SP2 for client first. After rolling our SP2 to Project 2007
Pro
we
will start installing SP2 on test and prod servers.


Problem situation:
All my colleaques from IT are reporting time (every week/day) on PWA.
There
are not problems with reporting time and importing timesheets (except
some
small problems sometimes). Whenone of our colleaques is added on
Resource
Plans and:
Work Units : days or hours
Column Interval: Months (the most popular and easy for everybody).

We have General Error message as described before.

I think that error is only on specific resource (but this resource has
no
problem with reporting time) We checked that account many times - seems
to
be
configured correctly as all others.

But Resource Plan works when Column Interval is set up for weeks - that
is
strange.


Thank you for any help.

BR
Rafal Paczynski



:

Rafal:

Are you planning on installing SP2 anytime soon? If so, I'd be curious
whether that resolves the issue, otherwise I'm leaning toward thinking
this
may be the result of corruption in the db. I want to be sure that I
understand that this problem only occurs with two specific resources?
If
that's the case, it points more toward those resource records than the
Resource plan functionality.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Hi Again,

I forgot to add, that in resource Plan:
Cloumn Interval - Months
Work units - Days (it is also failing with HOURS)

Thanks for help

Rafal Paczynski




:

Interesting, what language version are you using? This may be an
anomaly
in
Project Server or it may be locale specific. Can you share the
actual
error
messages? Do you see corresponding errors in the ULS logs?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Hi,

I just discovered something, when in resource Plan Column
Interval
is
set
up
for date different that Months we do not experience that error.
When I change beck to months I have General error message again.

We need to use Months as we use Resource Plans for planning.

Thank you for any help.


:

Hi Gary,

Thank you for replay.
Yes I am sure that this user is a resource who can be assigned
in a
project
plan. He is reporting his time on PWA everyday. Is no problem
with
reporting
time and importing timesheets.
Only one problem is when resource is assigned to Resource Plan.
Each
time
we
assign press Save or Save and Publish we have error General
error:
Work
value
used is invalid. (Use this error information along with other
errors
to
find
out the cause of the problem.)

I was also informed that that some problem is now for one more
resource.

BR
Rafal



:

Are you certain that Henrik is a resource that can be assigned
to
tasks
in a
project plan?

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com



Hello,

I have error message when works with Resource Plan. It
happens
for
one
user
only.That user is called Henrik, each time when we are
trying
to
save
Resource Plan after adding Henrik to the resource plan (we
tried
in
many
different resource plans each time is that some) we can see
GENERAL
ERROR.
I
was checking in databases and I can find resource plan under
Project
Published database\ MSP_RESOURCE_PLAN_ASSIGNMENTS. In this
table I
can see
other resources assigned to that resource plan (and that is
perfect).
In
this
table I can't see henrik account assigned to the resource
plan
howether
under
PWA web page I can see his account. Could you plase explain
to
me
if
is
any
temporary database where that account is so I can see it
under
PWA
before
pressing SAVE AND PUBLISH?

I was testing and on our test env (copy of prod) we do not
have
that
problem
with that resource, that is eaven more confusing for me.

That is error message for General error:

05/19/2009 12:02:09.10 w3wp.exe (0x1430)
0x1E6C Project Server Project Server -
General
8mqg Exception System.Web.Services.Protocols.SoapException:
System.Web.Services.Protocols.SoapException:
ProjectServerError(s)
LastError=GeneralWorkInvalid Instructions: Pass this into
PSClientError
constructor to access all error information at
Microsoft.Office.Project.Server.WebService.ResourcePlan.QueueUpdateResourcePlan(Guid
projectUid, ResourcePlanDataSet rpds, Boolean timephasedFTE,
Boolean
autoCheckIn, Guid jobUid) at
System.Web.Services.Protocols.SoapHttpClientProtocol.ReadResponse(SoapClientMessage
message, WebResponse response, Stream responseStream,
Boolean
asyncCall)
at
System.Web.Services.Protocols.SoapHttpClientProtocol.Invoke(String
methodName, Object[] parameters) at
Microsoft.Office.Project.Server.WebServiceProxy.PSIProxyBase.InvokePSI(String
serviceName, String methodNam...

ENV:
servers 2003 SP2 MS Project Server 2007 with December
Cumulative
updates.

Thank you in advance
Michal
 
R

Rafal_Paczynski

Hi,

I got replay from Microsoft consultant.
For now that is all I have, maybe can be usefull for anybody.
That is not permanent solution, if anybody can help here could be really
nice :)


I finally managed to find a way to reproduce the issue on your databases.

I found out that the problem lies if you set up a resource Calendar to have
a full month of vacation. It happens on months (and years, not on weeks and
days). (If the whole week is set to non working time and the week in the date
range covers the week, then the issue does not occur.)

If the whole month`s 4weeks is set as non working time and the 4 weeks are
running from Sunday to Saturday as with the very special month Feb which is
covering exactly 28 days - 4 whole weeks.

If one day in Feb 2009 is set to working day , then saving the res plan
works ok

This is occurring for different res. as well if we set the same calendar
exception as for Holger, therefore I suppose there is something wrong or
corrupt somewhere.
 
G

Gary L. Chefetz

Rafal:

I think that applying both the April CU and the hotfix described here
http://support.microsoft.com/default.aspx?scid=kb;en-us;971066&sd=rss&spid=11388
that the problem should go away. Please let me know if you test this theory,
and how it goes.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 

Ask a Question