T
Tom Godbold
MSPS 2007 / MS Project Pro 2k7
In Dale and Gary's book, they describe what I interpret as two different
ways to plan for resource capacity:
1) Set the Resource Max Units to reflect the resource's capacity to work on
Projects (a.k.a. Working Time spent on Projects, some call it "Productive"
time; NOT Administrative time).
Example:
Max Units = 75%
Capacity = 30 hours/week
2) Set the Enterprise Calendars to reflect capacity to work on Projects.
Example:
Enterprise Standard Calendar Working Time: M-F 9A - 12P; 1P - 4P
Capacity = 30 hours/week
I've tested both and they both have the same effect on Capacity.
So the question is-- Which one is the Best Practice? Or, if both are good,
why would you use one over the other?
**
Unsolicited Endorsement: As an EPM implementor and PMO Director, my best
advice to you is this: If you are implementing MOPS 2007, buy Dale and
Gary's books! They are the most comprehensive and well-organized books
available for MSPS. They give you practical advice, not just an overview of
capabilities and options. And no, I am in no way affiliated with
MSProjectExperts, nor am I receiving any kind of compensation for this
endorsement. These books have saved us tons of time and rework!
Managing Enterprise Projects using MOPS 2007
Implementing and Administering MOPS 2007
http://projectserverbooks.com
In Dale and Gary's book, they describe what I interpret as two different
ways to plan for resource capacity:
1) Set the Resource Max Units to reflect the resource's capacity to work on
Projects (a.k.a. Working Time spent on Projects, some call it "Productive"
time; NOT Administrative time).
Example:
Max Units = 75%
Capacity = 30 hours/week
2) Set the Enterprise Calendars to reflect capacity to work on Projects.
Example:
Enterprise Standard Calendar Working Time: M-F 9A - 12P; 1P - 4P
Capacity = 30 hours/week
I've tested both and they both have the same effect on Capacity.
So the question is-- Which one is the Best Practice? Or, if both are good,
why would you use one over the other?
**
Unsolicited Endorsement: As an EPM implementor and PMO Director, my best
advice to you is this: If you are implementing MOPS 2007, buy Dale and
Gary's books! They are the most comprehensive and well-organized books
available for MSPS. They give you practical advice, not just an overview of
capabilities and options. And no, I am in no way affiliated with
MSProjectExperts, nor am I receiving any kind of compensation for this
endorsement. These books have saved us tons of time and rework!
Managing Enterprise Projects using MOPS 2007
Implementing and Administering MOPS 2007
http://projectserverbooks.com