In Project Server, when is a change to a work resource rate table or say a
revision to a work resource's availability going to be seen in an a Project?
Is it the next time the Project file is opened, the next time it is saved,
the next time it is published?
 
J

Jonathan Sofer [MVP]

Changes to an enterprise resource should be seen in the project the next
time it is opened. Each time a project schedule is opened from the server,
it will read the latest information from the enterprise resource pool for
the resources that are on that project.

Jonathan
 