A
ABW
I need assistance with my new Resource Pool.
I have approx. 250 Shared links in a Resouce Pool that should now point to a
new SQL server name. So far, I've broken all links by opening my Resource
Pool and using Tools, Resource Sharing, Share Resources and selecting all
projects and I used the "Break Link" option.
Now I need to re-create all 250 links by opening each individual Project and
use Tools, Resource Sharing, Share Resources and choose "use own resources'
and then choose the new Resource Pool from the drop down menu...for EVERY
project!
There must be a faster way to re-create all links when changing servers,
right? Is there a utility or script available to make life easier?
btw, I'm running MS Project 2k3 (Standard edition), with an SQL 2000 database.
Thanks for any suggestions.
ABW
I have approx. 250 Shared links in a Resouce Pool that should now point to a
new SQL server name. So far, I've broken all links by opening my Resource
Pool and using Tools, Resource Sharing, Share Resources and selecting all
projects and I used the "Break Link" option.
Now I need to re-create all 250 links by opening each individual Project and
use Tools, Resource Sharing, Share Resources and choose "use own resources'
and then choose the new Resource Pool from the drop down menu...for EVERY
project!
There must be a faster way to re-create all links when changing servers,
right? Is there a utility or script available to make life easier?
btw, I'm running MS Project 2k3 (Standard edition), with an SQL 2000 database.
Thanks for any suggestions.
ABW