Hello,
I am assigning resources from a resource pool to individual projects for my
group. I'd like to make it so resources are assigned a Max Unit % on
individual projects, but maintain a Max Unit % of 100% in the resource pool.
So, for instance, resource 1 is available 100% in the pool, but only 50% to
project 1 so that assigning this resource to a 1-day task results in 4 hours
work on project 1 that day.
Is this possible?
Thank you,
Tom