M
Mark E
Hello,
I have many sharer files / projects linked into a resource pool. It has
been decided to more accurately reflect what a working day is. So I changed
the default standard calendar / standard working time to reflect a 6.5 hrs
per week (from 8hrs), and 32.5 hrs/week (from 40hrs).
All my projects are fixed duration, so I assumed that none of the durations
would change within any of the sharer files / projects linked to the pool.
This was correct for the tasks that did not have any work complete on them
(ie: 0% for % work complete). In other words, if a task had > 0% work
complete then the duration for that task would be recalculated.
Is there a way to stop it from recalculating? What am I missing? I don't
want to have to go back and adjust all those tasks that could potentially be
adjusted. Thanks!
Mark
I have many sharer files / projects linked into a resource pool. It has
been decided to more accurately reflect what a working day is. So I changed
the default standard calendar / standard working time to reflect a 6.5 hrs
per week (from 8hrs), and 32.5 hrs/week (from 40hrs).
All my projects are fixed duration, so I assumed that none of the durations
would change within any of the sharer files / projects linked to the pool.
This was correct for the tasks that did not have any work complete on them
(ie: 0% for % work complete). In other words, if a task had > 0% work
complete then the duration for that task would be recalculated.
Is there a way to stop it from recalculating? What am I missing? I don't
want to have to go back and adjust all those tasks that could potentially be
adjusted. Thanks!
Mark