C
Carrie
I did not baseline my resource pool 3 weeks ago when work assignments were
published and now I need to create a work "variance" report by resource. I
need help creating a baseline based on work planned using project files I
have from November 13th. I did baseline the project files...just NOT the
resource pool. then I need to create a report to show work baselined by
week and actual work by week by resource.
published and now I need to create a work "variance" report by resource. I
need help creating a baseline based on work planned using project files I
have from November 13th. I did baseline the project files...just NOT the
resource pool. then I need to create a report to show work baselined by
week and actual work by week by resource.