Resource Pool changes actual hours in 2010

Joined
Jul 13, 2012
Messages
3
Reaction score
0
I have a project in MS Project 2010. After I attach it to a resource pool I noticed the actual hours previously applied to the plan changed in certain weeks but only for certain resources. I'm getting numbers like .07 hours per week for 10 or 11 weeks in a row where there were previously zero with a .75 in the final week. Any idea what causes this? The total actual hours for the project seem to be correct but the weekly totals are now off.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top