S
Steve Scott
Hi, When I first connect a sharer file to a resource pool I notice
immediately that the start and end dates changes on some of the tasks - why
is this becuase at this point I haven't changed any tasks or assignments?
Could it be something to do with Calendars per se or might it be the Local
resources in the plan clash with the RP?
immediately that the start and end dates changes on some of the tasks - why
is this becuase at this point I haven't changed any tasks or assignments?
Could it be something to do with Calendars per se or might it be the Local
resources in the plan clash with the RP?