Resource Pool connection changes start and finish dates

S

Steve Scott

Hi, When I first connect a sharer file to a resource pool I notice
immediately that the start and end dates changes on some of the tasks - why
is this becuase at this point I haven't changed any tasks or assignments?
Could it be something to do with Calendars per se or might it be the Local
resources in the plan clash with the RP?
 
J

JulieS

Hi Steve,

I'd check the resource's calendars. The scheduling of tasks is
initially set by a number of things -- one of which is the project
calendar. If you have resources assigned to tasks -- a change in
the resource's calendar will impact tasks.

You appear to be using Project Server -- if my response doesn't
help -- I suggest re-posting to the server newsgroup.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 