PK Consulting
I’m working with a small company trying to help one of their departments
implement some best management practices. I’m trying to stay away from a full
blown EPM implementation and I’m trying to create a “pseudo enterprise poolâ€.
I want to do the following:
· Assign tasks to Resource 1 in Plan A
· Assign tasks to Resource 1 in Plan B
· Import Plans A and B into Plan C – I’d like the Resource Usage
view to only show one Resource 1, with the tasks assigned to him in Plan A
and Plan B.
Any ideas?
implement some best management practices. I’m trying to stay away from a full
blown EPM implementation and I’m trying to create a “pseudo enterprise poolâ€.
I want to do the following:
· Assign tasks to Resource 1 in Plan A
· Assign tasks to Resource 1 in Plan B
· Import Plans A and B into Plan C – I’d like the Resource Usage
view to only show one Resource 1, with the tasks assigned to him in Plan A
and Plan B.
Any ideas?