Hi;
We've recently moved from Project 2003 to Project 2007 SP2 (without the
server at this moment). There were 150+ project plans that were to be saved
as Project 2007, including the resource pool. However when a project plan is
saved and I click on 'update resource pool' message, it takes unusually long
time to save / update the resource pool.
Earlier (with project 2003) if it was taking 15 seconds to update the pool,
now its taking more than a minute for the same. Can the experts provide any
suggestions to improve this time?
We've recently moved from Project 2003 to Project 2007 SP2 (without the
server at this moment). There were 150+ project plans that were to be saved
as Project 2007, including the resource pool. However when a project plan is
saved and I click on 'update resource pool' message, it takes unusually long
time to save / update the resource pool.
Earlier (with project 2003) if it was taking 15 seconds to update the pool,
now its taking more than a minute for the same. Can the experts provide any
suggestions to improve this time?