Joe said:
How do I create a resource table that indicates I have used a resource pool?

Thanks

I assume you want to use a shared resource pool. Best first step would
be to search Project's Help for the article "Share resources using a
resource pool".
 
J

Jan De Messemaeker

Hi,

In Resource Usage view show the column Project. It will show the name of the
pool for the resources, of the relevant projects for the assignments.
Greetings,

--
Jan De Messemaeker