Resource pool

F

Fred

I am trying to create a resource pool that several projects can utilize, but at the same time create resources that only I can utilize (labor). So far I have created a resource pool, but whenever I create a new resource in my project, if the resource pool is open, the new resource I create in my project appears in the pool. Is there something I am doing wrong, or is it not possible to do what I want?
 
D

Dale Howard [MVP]

Fred --

By default, any resource with task assignments in a sharing project is
automatically added as a resource in the shared resource pool. You are not
doing anything wrong, as this is the default behavior of a shared resource
pool. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Fred said:
I am trying to create a resource pool that several projects can utilize,
but at the same time create resources that only I can utilize (labor). So
far I have created a resource pool, but whenever I create a new resource in
my project, if the resource pool is open, the new resource I create in my
project appears in the pool. Is there something I am doing wrong, or is it
not possible to do what I want?
 