Resource Pool

T

Tan777

We linked resource pools and now we cannot figure out why we have resources
that are over allocated and we cannot change the information to remove the
red overallocations.
 
J

John

Tan777 said:
We linked resource pools and now we cannot figure out why we have resources
that are over allocated and we cannot change the information to remove the
red overallocations.

Tan777,
You linked resource pools? If you did, that's asking for trouble. Links
between files, (including those to a resource pool), are subject to
corruption if the link structure is too complex and/or the files are
heavily edited.

I suggest you clean up the file structure and only use one resource pool.

John