Resource Pooling and client rates

N

neil.middleton

I'm trying to figure out how to solve an issue I have, and it's not
overly apparent to me.
Basically, I want to link many projects to a shared resource pool so
that I have a single point of entry for holidays, working hours etc
(we're a web development agency). This is so we can track resource
usage, and scheduling around holidays etc. This is all working fine.

However, I would like to set different rates for resource on different
projects. ie Person A might cost $300 to Client A, versus $500 for
Client B.

How can I set this up? Is it possible?

Neil
 
J

Jonathan Sofer

Neil,

This is not possible to do when you go to a shared resource pool model
because rate is a resource attribute and not a project or "resource on
project" attribute, . The same issue occurs in the enterprise server
version when the model switches to an enterprise resource pool. Any attempt
to change resource data like rate on the project will be overwritten from
the enterprise resource pool or shared resource pool each time the project
is opened.

Jonathan
 
N

neil.middleton

In that case how can I go about resource levelling if resources
applied to projects are seperate entities in the eyes of Project. As
I see it, Project won't be able to level Project A's "bob" vs Project
B's "bob". Also, how do people manage multiple projects and staff
holiday etc?

Neil
 
J

JulieS

Hello Neil,

You can accomplish what you need by using the Cost rate tables and
then assigning the different rate table to the resource's assignment.

Double click on the Resource's name to show the Resource Information
dialog box. Click the Costs tab and enter a rate for each tab (A, B,
C, etc.)

Once you assign the resource to tasks, view the Resource Usage view
and add the Cost Rate Table field to the table (left side). Select
the correct cost rate table for the resource on the specific
assignments.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top