D
DominoStarnes
Software Versions: Project 2002 Professional and Project 2003 Professional
(I've tried this in both versions)
SUMMARY OF ISSUE: I am attempting to define a daily maintenance task in a
separate project file which is intended to take up 50% of a resource's daily
time (resource is defined in a resource pool and the maintenance task is
defined in a separate project file). Ideally, this "daily maintenance task"
would be 50% of the resource's allocated time and the other project's tasks
would fill in using the remaining available time. To accomplish this, I've
assumed that I would assign a "50%" value for the units of the individual
task to which the resource is assigned in the separate project file which
contains the daily maintenance task. However, the result has consistently
been that the resource is only scheduled for the single "maintenance task"
and the total hours which the resource is scheduled is reduced to whatever
percentage is assigned in the reduced units value.
QUESTION: How can I get Project to schedule a set percentage of time to one
project’s task and fill in the remaining time with dynamically adjusting
project tasks from other projects?
(Any and all help/assistance is gratefully appreciated!)
(I've tried this in both versions)
SUMMARY OF ISSUE: I am attempting to define a daily maintenance task in a
separate project file which is intended to take up 50% of a resource's daily
time (resource is defined in a resource pool and the maintenance task is
defined in a separate project file). Ideally, this "daily maintenance task"
would be 50% of the resource's allocated time and the other project's tasks
would fill in using the remaining available time. To accomplish this, I've
assumed that I would assign a "50%" value for the units of the individual
task to which the resource is assigned in the separate project file which
contains the daily maintenance task. However, the result has consistently
been that the resource is only scheduled for the single "maintenance task"
and the total hours which the resource is scheduled is reduced to whatever
percentage is assigned in the reduced units value.
QUESTION: How can I get Project to schedule a set percentage of time to one
project’s task and fill in the remaining time with dynamically adjusting
project tasks from other projects?
(Any and all help/assistance is gratefully appreciated!)