Hi
I currently using ms-project 2003 professionnal. We installed project server
2003 to be able to manage our ressources more effiiciently.
I have a Project where all the ressources are defined without any task. It
has been insert into Ms-Project has a administrative project to manage
non-working time.
I'm working on a project whish has been check-in into project server and
when I want to assign a resource from entreprise resource from the Build
Team box, it contain no resource.
I expected to get all the resources already defined in the Non Working time
project as my resource dictionnary.
In Project Server side, we created few resources but none appear when I go
to Resource Center. Is it normal?
How can I created this entreprise pool to be able to use the resources?
Any idea?
Thanks
I currently using ms-project 2003 professionnal. We installed project server
2003 to be able to manage our ressources more effiiciently.
I have a Project where all the ressources are defined without any task. It
has been insert into Ms-Project has a administrative project to manage
non-working time.
I'm working on a project whish has been check-in into project server and
when I want to assign a resource from entreprise resource from the Build
Team box, it contain no resource.
I expected to get all the resources already defined in the Non Working time
project as my resource dictionnary.
In Project Server side, we created few resources but none appear when I go
to Resource Center. Is it normal?
How can I created this entreprise pool to be able to use the resources?
Any idea?