A
Anatess
Hi,
I've googled all day long for an answer but all I found were similar
questions with no answers. I'm hoping you can answer my question or lead to
me to a site that may have the answer.
I'm trying to understand where the resource rates are found on the tables.
I found MSP_RESOURCE_RATES table, but it looks like this table only gets
populated when the resource is assigned to a project. But, when I open the
enterprise resource pool cost tab there are rates in there before I even
assign the resource to a project. So, what table are these rates stored?
By the way, I'm not in IT so I don't have access to a developers workbench.
All I can use is a query tool that has a read-only connection directly to the
project server tables. I've been able to structure basic adhoc queries even
figuring out outline codes. But this rate table is stumping me!
Thank you for your assistance.
I've googled all day long for an answer but all I found were similar
questions with no answers. I'm hoping you can answer my question or lead to
me to a site that may have the answer.
I'm trying to understand where the resource rates are found on the tables.
I found MSP_RESOURCE_RATES table, but it looks like this table only gets
populated when the resource is assigned to a project. But, when I open the
enterprise resource pool cost tab there are rates in there before I even
assign the resource to a project. So, what table are these rates stored?
By the way, I'm not in IT so I don't have access to a developers workbench.
All I can use is a query tool that has a read-only connection directly to the
project server tables. I've been able to structure basic adhoc queries even
figuring out outline codes. But this rate table is stumping me!
Thank you for your assistance.