Resource Rates In Database

G

Greg

I have an installation of Project Server 2003, and an enterprise
resource pool. I need to be able to set resources standard rates, along
with the effective dates. I understand how to do this from the user
interface, but is there a way to do this programmatically? I am a
certified .NET developer.

I have looked at the msp_resource_rates table, but it appears that
information is only stored in that table after the rates for the
enterprise resources have been applied to the project. Where are the
"master" rates stored?

I have even tried deleting all rate information from the
msp_resource_rates table, but as soon as a project is opened in Project
Pro, and then saved the table is repopulated.

Thanks in advance.
 