Resource Rates

R

Robin Roe

Hi

We work in an environment where from project to project a specific resource
will have a different rate, to the extent that almost all projects have
unique rates. Pre Project Server days this was fine in that you could specify
a different rate for each independent project, but now unfortunately we can
only have a choice of 5. Is there any way to have independent rates for
resources for each project without loosing the organisation wide resource
loading information that Project Server gives us.

Thanks for your help
 
D

Dale Howard [MVP]

Robin --

The system restricts you to only five rates per resource in the Enterprise
Resource Pool. Sorry.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top