Hi Duncan --
The two methods that Marc mentions are correct, but the required method
depends upon whether or not your Project Server is configured for
Managed Timesheet Periods.
If your organization IS using Managed Timesheet Periods -- assuming
that the Team Members cannot / will not adjust their own Remaining Work
via PWA Timesheets -- then you must use the first method (Adjust
Actuals).
If your organization IS NOT using Managed Timesheet Periods, then you
must use the second method (adjustment via Project Pro). Marc mentions
using the Resource Usage view, but you can also use the Task Usage
View. They are very similar (both show task assigments), but the
Resource Usage view groups the assignments by resource, and the Task
Usage view groups the assignments by task.
Good luck!