jlbreyer
The engineering manager wants to see resources vs projects for a month at a
time. My problem is that he wants to see ALL resources, even if the
individual has no hours assigned. I can show all resources by going to
Commands and Options and setting Always show empty rows. My problem comes
when I add a field to the rows for sorting or grouping the engineers. When I
do that, I see all groups on every resource row.
I think my question is: how can I show all resources assigned work vs all
active projects and sort/group the resources by discipline?
I have figured out a couple work-arounds, but they are very clunky and need
a lot of maintenance.
time. My problem is that he wants to see ALL resources, even if the
individual has no hours assigned. I can show all resources by going to
Commands and Options and setting Always show empty rows. My problem comes
when I add a field to the rows for sorting or grouping the engineers. When I
do that, I see all groups on every resource row.
I think my question is: how can I show all resources assigned work vs all
active projects and sort/group the resources by discipline?
I have figured out a couple work-arounds, but they are very clunky and need
a lot of maintenance.