M
Mike G
Okay, the bain of my existance right now is that some of my resources have
changed and so has thier involvement on any one task.
Let's say that I have five (5) resources for one task and that I have an
estimated amount of money and time to be used based on my plan. Let's also
say that I have resource #3 set to complete 30% of the work required and
resource #4 to do 40%. As resource #3 gets involved, they start to go over
thier expected hours while resource #4 needs much less. Since I have entered
resource #3 to use 30% and resource #4 to use 40%, my costs are now skewed.
As I rebaseline the project I adjust thier percentages, which becomes a
headache.
The headache is because I don't know how to change thier hours or %'s to get
the correct EAC without recalculating thier current % of funds/hours.
I have to be doing something really silly since this can't be the first time
this has appeared.
Someone, anyone care to chime in. An expert would be great!?!?
Mike
changed and so has thier involvement on any one task.
Let's say that I have five (5) resources for one task and that I have an
estimated amount of money and time to be used based on my plan. Let's also
say that I have resource #3 set to complete 30% of the work required and
resource #4 to do 40%. As resource #3 gets involved, they start to go over
thier expected hours while resource #4 needs much less. Since I have entered
resource #3 to use 30% and resource #4 to use 40%, my costs are now skewed.
As I rebaseline the project I adjust thier percentages, which becomes a
headache.
The headache is because I don't know how to change thier hours or %'s to get
the correct EAC without recalculating thier current % of funds/hours.
I have to be doing something really silly since this can't be the first time
this has appeared.
Someone, anyone care to chime in. An expert would be great!?!?
Mike