J
JimS
I must be going nuts. I need to assign a role to a task with a duration of 90
days, and have him only devote a total of 90 hours to that task over the
entire 90 days' duration.
When I assign the role, and change the BLU to 90, it changes the OD to 11.
If I go back and change the OD back to 90, P6.1 sets the RD to (90-11) 79. If
I then go and change the RD to 90, it resets the Role's BLU to 720. It's a
big circle I need to escape. I've never had this issue in P3. What am I doing
wrong? Some setting? I looked, but I just can't figure it out.
Basically, I need a role to spend only an hour a day on this task for a
duration of 90 days. How do I do that?
days, and have him only devote a total of 90 hours to that task over the
entire 90 days' duration.
When I assign the role, and change the BLU to 90, it changes the OD to 11.
If I go back and change the OD back to 90, P6.1 sets the RD to (90-11) 79. If
I then go and change the RD to 90, it resets the Role's BLU to 720. It's a
big circle I need to escape. I've never had this issue in P3. What am I doing
wrong? Some setting? I looked, but I just can't figure it out.
Basically, I need a role to spend only an hour a day on this task for a
duration of 90 days. How do I do that?