J
Jesse
I'd like to identify the resource role in tasks in my schedule. I'm using MS
Project 2003 and Project Server 2003. In many of the tasks I'd like to
identify who the owner is and who the resource is.
- on task 1 Billy if the owner, Betty is the facilitator, and Bobby is a
resource
- on task 2 Betty is the owner, Billy is the facilitator, and Bobby is a
resource
- on task 3 Bobby is the owner, Billy is the facilitator, and Betty is a
resource
The only way I know to do this is have multiple resources for each resource
-- Billy (owner), Billy (facilitator), Billy (resource). I don't want to have
multiple resources for each resource. How can I do the resource role by task
without having multiple resources per resource?
Project 2003 and Project Server 2003. In many of the tasks I'd like to
identify who the owner is and who the resource is.
- on task 1 Billy if the owner, Betty is the facilitator, and Bobby is a
resource
- on task 2 Betty is the owner, Billy is the facilitator, and Bobby is a
resource
- on task 3 Bobby is the owner, Billy is the facilitator, and Betty is a
resource
The only way I know to do this is have multiple resources for each resource
-- Billy (owner), Billy (facilitator), Billy (resource). I don't want to have
multiple resources for each resource. How can I do the resource role by task
without having multiple resources per resource?