B
Bob
Just because you have a resource that is working M-F 8am-5PM doesn't mean
that they have all that time available to work on your project.
how can you go in and say that some resource has N Hours per day,
irrespective of what TIME those hours are applied?
In other words, say i have a resource in a matrix environment that can give
me 4 hours of Project Work. I don't care, as a PM, if it's from 8am to noon,
2 hours in the AM, 2 hours in the PM, etc. I care that he's allocated on my
plan for 4 HOURS of Project work for that day. Maybe on MWF he can give me 4
hours, and on TUES / Thurs he can give me 6 hours.
again, i don't care what time he books them in, as long as he's applied in
my calendar at the hours he can give me.
when i book him now, i have him setup as a resource who works M-F 8am to
5pm. When Project books him as a resource, it allocates all those hours.
That's not realistic.
I need to be able to say that John Doe is available N Hours per day on M, T,
W, N+2 hours on Th /Fr. and not actuually book a time frame.
that they have all that time available to work on your project.
how can you go in and say that some resource has N Hours per day,
irrespective of what TIME those hours are applied?
In other words, say i have a resource in a matrix environment that can give
me 4 hours of Project Work. I don't care, as a PM, if it's from 8am to noon,
2 hours in the AM, 2 hours in the PM, etc. I care that he's allocated on my
plan for 4 HOURS of Project work for that day. Maybe on MWF he can give me 4
hours, and on TUES / Thurs he can give me 6 hours.
again, i don't care what time he books them in, as long as he's applied in
my calendar at the hours he can give me.
when i book him now, i have him setup as a resource who works M-F 8am to
5pm. When Project books him as a resource, it allocates all those hours.
That's not realistic.
I need to be able to say that John Doe is available N Hours per day on M, T,
W, N+2 hours on Th /Fr. and not actuually book a time frame.