Resource Scheduling

R

Rohan

Hi,

We need to assign a task to a group of people, i am not sure how EPM handles
this. Can we treat the entire group as one resource ? The requirement is that
group can handle about 600 hrs of work in a week. The resource who is going
to work on the task is undetermined. There are different such groups with
different capacity.

Please let me know.

-Rohan
 
G

Gérard Ducouret

Hello Rohan,

You can create Generic Resource : Check the "Generic" check box in the
Resource Information dialog. For that resource, set the Maxi Units to 15 for
example.

Gérard Ducouret
 
R

Rohan

Hi Gérard,

Thank you for your quick response. What happens if a resource is allocated
more than max units ?

-Rohan
 
G

Gérard Ducouret

It'll appear with a red color in the Resource Sheet: that means
"overallocated". The Leveling feature can solve the problem if it is
generated by two tasks running in parallel.

Gérard Ducouret
 