resource scheduling

K

K

This may be 2 dumb quesitons, please humor me. I have a resource that is
available to the project a gaurenteed 50 % of their time. I don't really
care when during the week I get this time with the exception of schedueled
meetings. Do I level this resouce at 4 hours per day x 5 days load it up in
2.5 days? End the end the effect is the same correct?

Second Question: With only one resouces assigned to the project at 50% of
thier time that makes everytime a Finish to start relationship with
occasional negative lag and the occasional split task accounting for any
concurrent acitities. Am I missing something here?

Regards
k
 