Resource Sheet Question

T

Té

On the Resource Sheet when you change a resource's availability to part time,
how come the max units goes to 0%?

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...e14d7b1123&dg=microsoft.public.project.server
 
J

Jan De Messemaeker

Hi,

Same question as on the other post: where did you change the resource's
availability? My hunch is that you did that in the availability from-to
window.
That means the resoruce's max units vary in time.
What you see in the resource sheet is the Max Units as of NOW.
That will than be 0%.
You probably set 50% from Date1 to Date 2: that leaves the rest of infinity
to 0%.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
T

Té

THANK YOU SOOOOO MUCH!!!!

Jan De Messemaeker said:
Hi,

Same question as on the other post: where did you change the resource's
availability? My hunch is that you did that in the availability from-to
window.
That means the resoruce's max units vary in time.
What you see in the resource sheet is the Max Units as of NOW.
That will than be 0%.
You probably set 50% from Date1 to Date 2: that leaves the rest of infinity
to 0%.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
T

Té

Thanks again! How does Microsoft Project know which tasks fall into the
critical path? Is it based on the dependencies?
 
J

Jan De Messemaeker

Hi,

On dependencies AND constraints if any. Project does a forward calculation
to determine the earliest start date (constraints and epe,ndencies can come
in) and also a backward pass to calcukate the latest start date. For a
critical task both dates coincide.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

Mike Glen

Hi Té,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #1 and the reference to Network Analysis, at
this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top