J
Julie
Hi All
We are implementing a number of projects using a shared resource pool.
Four of our resources are utilised on the Help Desk so I have created
a project called "Help Desk" on which I want to put these four
operators.
The problems I have are:
1) these people work rotating shifts on a four weekly basis with
overlapping hours – is there any way of implementing these hours for
the staff without having to individually edit their resource calendars
as the projects I am look at span the next five years
2) these people have different skill sets and need to be able to be
utilised on other tasks within the project and on other projects.
However, there needs to be at least one person on the Help Desk at any
one time. So I need to be able to assign them to a task called "Help
Desk" and then pull them off this to work on other tasks & projects as
the need arises.
The only ways I can figure out how to do this is:
1) create four tasks, one for each shift – assign the resources at
100% to each of the tasks and then manually edit the hours they are
working in the Resource Usage view
2) create a task called "Help Desk", edit the resources individual
calendars to reflect the shifts they are working on and then assign
all the resources to the task and then use the Resource Usage view to
see where they overlap so that I can then utilise them at that time on
other tasks / projects.
Are either of the options the best way to approach the situation or
does anyone have a better solution.
Using Project 2003 Professional.
TIA
We are implementing a number of projects using a shared resource pool.
Four of our resources are utilised on the Help Desk so I have created
a project called "Help Desk" on which I want to put these four
operators.
The problems I have are:
1) these people work rotating shifts on a four weekly basis with
overlapping hours – is there any way of implementing these hours for
the staff without having to individually edit their resource calendars
as the projects I am look at span the next five years
2) these people have different skill sets and need to be able to be
utilised on other tasks within the project and on other projects.
However, there needs to be at least one person on the Help Desk at any
one time. So I need to be able to assign them to a task called "Help
Desk" and then pull them off this to work on other tasks & projects as
the need arises.
The only ways I can figure out how to do this is:
1) create four tasks, one for each shift – assign the resources at
100% to each of the tasks and then manually edit the hours they are
working in the Resource Usage view
2) create a task called "Help Desk", edit the resources individual
calendars to reflect the shifts they are working on and then assign
all the resources to the task and then use the Resource Usage view to
see where they overlap so that I can then utilise them at that time on
other tasks / projects.
Are either of the options the best way to approach the situation or
does anyone have a better solution.
Using Project 2003 Professional.
TIA